INOX - type Vibration Isolators

Made of acid-resistant steel OH18N9T and white EPDM rubber resistant to:

  • Acids: fluoroboric, formic, fluorosilicic, acetic, propionic
  • Caustic potash and soda
  • Substances like: ethyl ascetate, methyl isobutyl ketone, methyl ketone, isobutyl acetate, isopropyl acetate, etc.

WARNING !

Do not use with oils and greases.

TO optimize the selection of a vibration isolator one should consider:

  • device’s operating condition
  • device’s full mass
  • amount of points of support
  • load concentration on a point of support
  • rotational speed of spinning/rotating elements

INOX type bowl vibration isolators selection and construction data tables.

inox wm
Type and size Axial load range[kg] Dimensions [mm] Mass 1 pc.
D H M h*
INOX – 4 10 – 60 42 77 M10 26 0,15
INOX – 8 60 – 200 82 100 M12 34 0,40
  INOX – 12 200 – 500 122 133 M16 41 1,20
©All rights reserved.
* without load

 

Vibration isolator’s marking:
Bowl vibration isolator X-Y
X– INOX type
Y – vibration isolator’s size (4-12)

Exemplary order:
Bowl vibration isolator INOX -8 pcs.

Charakterystyki wibroizolatorów miseczkowych typu INOX.

INOX – 4 INOX – 8
inox inox
INOX – 12
inox

WM bowl vibration isolators mounting in unthreaded through holes

gb gb

Order of operations:

  1. lift a machine
  2. slide the vibration isolators under the holes in the base of a machine
  3. lower a machine inserting the mounting screws into the holes in the base of the machine
  4. level a machine by turning the lower leveling nuts right – lifting, left – lowering, level evenly on all mounting screws
  5. secure the leveling of a machine by clamping a spring washer on the mounting screws using the upper locknut
  6. verify the leveling of a machine after ca 1 week of operation and correct the leveling if required.

A machine should be leveled at a minimal distance from the floor.

WM bowl vibration isolators mounting in threaded through holes

gb gb

Order of operations:

  1. lift a machine
  2. screw the vibration isolator’s mounting screws into the threaded holes in the base of a machine
  3. lower the machine with the screwed in vibration isolators
  4. level the machine by turning the mounting screws right – lifting, left – lowering, level evenly on all mounting screws. Relieve the load on the vibration isolator before leveling.
  5. secure the leveling of a machine by clamping a spring washer on the mounting screws using a locknut
  6. verify the leveling of a machine and the upright position of the mounting screws after ca 1 week of operation and correct the leveling if required.

A machine should be leveled at a minimal distance from the floor.

 

WM bowl vibration isolators mounting in unthreaded blind holes

gb gb

Order of operations:

  1. lift a machine
  2. screw the mounting screws into the threaded holes in the base of a machine
  3. lower a machine with the screwed in vibration isolators
  4. level the machine by turning the mounting screws right – lifting, left – lowering, level evenly on all mounting screws. Relieve the load on the vibration isolator before leveling.
  5. secure the leveling of a machine by clamping a spring washer on the mounting screws using a locknut
  6. verify the leveling of a machine after ca 1 week of operation and correct the leveling if required.

A machine should be leveled at a minimal distance from the floor.